We did our walk through the house this week. The whole point of the walk through is to find things that need to be fixed. Most of the stuff that we found were paint that needs touch upped and the master bathroom floor needs to be fixed and that is it! We have locked in our interest rate, our appraisal is back and we are closing Tuesday, Jan. 25th!
Thursday, January 20, 2011
Walk Through
Sunday, January 16, 2011
The House is Done!
Well, basically the house is done! We have a walk through on Monday afternoon. And then we should close on the 26th and get the keys! This very long stressful ordeal is almost over!
Monday, January 10, 2011
Home Blue Home
So, they finally got the front of the house painted. The sides and back of the house is stucco and the front of the house is siding. I picked a beach sand color for the stucco and a denim blue for the front and a red door. I was hoping for a beach house feel.
All I can say is that our house definitely sticks out in the neighborhood.
I have to say that I (Rachel) am not loving my choices. I don't know if I don't like the blue or the tan and blue together. But, I made my choice and now I have to live with it. I am hoping that with a fence and some landscaping the blue will mellow out a bit.
Somebody told me to put some big BYU letters up and act like I am a big die hard fan. That might work since we live in Utah county.
The good thing is that I won't even need to tell people our address. All I will have to say is come to the blue house.
I have been having nightmares all last night of my 2 real estate brother-in-laws shaking their heads in shame at me. I had nightmares of them yelling at me "resale value!! resale value!!" Good thing we will be living here for a very loooonnnng time.
Friday, January 7, 2011
Sunday, January 2, 2011
January Starts
When we returned from California we wanted to go by and see the house.

They got the cabinets installed the some of the flooring in.
Bathroom cabinet and flooring.
Walls and trim painted. This is the family room.
The door goes out to the backyard.
They installed the hardware and doors in the house. This is part of the master bedroom closet.
They got the cabinets installed the some of the flooring in.
The door goes out to the backyard.
Whats left.
1) Electrical finish. (outlets, switches and lights)
2) Plumbing (install the faucets, toilets and sinks)
3) Carpet
4) Final stucco coat and siding on the house
5) Garage door
6) Walk through with the builder
7) Touch Ups
8) Move in January 26th
1) Electrical finish. (outlets, switches and lights)
2) Plumbing (install the faucets, toilets and sinks)
3) Carpet
4) Final stucco coat and siding on the house
5) Garage door
6) Walk through with the builder
7) Touch Ups
8) Move in January 26th
December Ends
Thursday, December 16, 2010
Insulation, Dry Wall, Walkway and Stucco
Monday they insulated the house. Yesterday the started dry walling the house. Today the were putting the mud on. The scaffolding is sitting around the house and will go up in the next day to start the exterior. Our walkway, steps and door pads were poured. The house is coming along.